Construction Updates

All Hwy 97 Ramps Open!

 
I-35 NORTH METRO SPLIT

UPDATE 10/23:
Highway 97 ramp to I-35 south is open!
Northbound I-35 exit ramp at Highway 97 is open!


 

Please see the map for other alternative routes.

Drivers can also follow posted detours: VIEW MAP

 
About this project
Six miles of I-35 from just south of the I-35 split to a half mile north of Hwy 8 at the Chisago/Washington county line will be resurfaced. Road resurfacing helps to preserve and extend the use of the pavement. The work will also include replacing three bridges.

Summary of work
Resurface existing pavement
Replace the Hwy 97 bridge over I-35 with a diverging diamond interchange for better traffic flow and improved safety
Update crosswalks at Hwy 97 to meet modern accessibility standards
Replace the flyover ramp from WB Hwy 8 to SB I-35 with a loop ramp
Drainage improvements
 

CURRENT TRAFFIC UPDATES


Stay Connected with MnDOT

Twitter
@mndottraffic: Be the first to know about Twin Cities Metro Area traffic incidents
@mndotnews: Get MnDOT news releases from across the state

Email Updates
Sign up for one or more of our email lists and stay up-to-date on current and planned construction projects and more.

Facebook
MnDOT—Our main page reporting on Minnesota’s multimodal transportation system as it maximizes the health of people, the environment and our economy

Upcoming Closures

Spring through summer 2019
Long-term I-35 lane closures will occur between the I-35W/I-35E split and Hwy 97
I-35W and I-35E may be reduced to a single lane at times, just south of the split
The NB I-35 ramps to and from Hwy 97 will close for approximately one month
 
Summer through fall 2019
Long-term I-35 lane closures will continue between the I-35W/I-35E split and Hwy 97
I-35W and I-35E may continue to be reduced to a single lane at times, just south of the split
The SB I-35 ramps to and from Hwy 97 will close for approximately one month
 
For up-to-date MnDOT info please CLICK HERE